132 kV Cable Double Circuit Connection Between
The New 400/132kV G/S at BAHIA and The 132/22kV S/S at YAS ISLAND

The scope of work of this project comprises the route survey, identification of existing services / cables along the cable route, design, manufacture, transport, erection, installation, jointing, termination, testing, commissioning and handing over in satisfactory condition of the following power cable and fibre optical cable circuits including all accessories, related earth and civil works, and equipment necessary for the proper survey, installation, connection and operation. The entire Scope of Work/Scope of Supply consists of the following:

  • Two complete (3-phase) cable circuits of single core cross-linked polyethylene (XLPE) insulated cables 132kV, 1200 mm2 copper conductor
  • Two complete optical fibre cable with 144-fibres per circuit

1. SPAN No. 1 Circuit 1 & 2 – excavation works, cable laying, pipes laying for FOC and backfilling done. Cable laid inside the substation ,
GIS Termination works pending
2. SPAN No. 2 – 11. Circuit 1 & 2 – excavation works, cable laying, pipes laying for FOC, route marker fixing and backfilling done.

3. SPAN No. 12 Circuit 1 & 2 – under progress (HDD Ongoing)

4. SPAN No. 13 Circuit 1 & 2 – Cable Laying completed. Pipes laying for FOC completed.

5. SPAN No. 14 Circuit 1 & 2 – under progress (NDRC works ongoing)

6. SPAN No. 15 Circuit 1 & 2 – Cable Laying completed. Pipes laying for FOC completed.

7. SPAN No. 16 & 17 Circuit 1 – Trench Excavation Cable Laying, FOC Pipe Laying complete